Global electricity use by data centers could double by 2030 as the artificial intelligence boom adds pressure to power grids across the world, according to the International Energy Agency.
Data centers could consume approximately 1,000 terawatt-hours of electricity a year by 2030 under the IEA's Stated Policies Scenario. Tight supply chains, local opposition and limited grid capacity could slow construction, the agency said.
The build-out is drawing major investment. The world's largest data center operators are expected to spend more than $700 billion in 2026, mostly on new infrastructure, the IEA said in a separate report published in April. Data center electricity use grew 17% in 2025, compared with 3% growth in global electricity demand.
The IEA cites large data center project pipelines in Texas, Virginia, Finland and the U.K. In several regions, the combined capacity of data centers waiting to connect exceeds current peak demand.
Without grid upgrades, power networks could become more congested and less reliable, the IEA warned in its Stated Policies Scenario, which incorporates policy measures formally put forward but not yet adopted. New projects could face longer waits to connect, while generators could be forced to cut output when the grid cannot meet demand.